Renewable energy
The planning process for a wind energy facility can be complex.
Victoria has abundant wind resources, and wind energy facilities have the potential to provide for a significant proportion of Victoria’s growth in electricity consumption. Victoria’s wind resources are considered well suited to supporting a large-scale grid of connected wind energy facilities.
What is a wind energy facility?
A wind energy facility is defined in clause 73.03 (Land use terms) of the Victorian Planning Provisions (VPP) as:
Land used to generate electricity by wind force. It includes land used for:
- any turbine, building, or other structure or thing used in or in connection with the generation, of electricity by wind force
- an anemometer.
It does not include turbines principally used to supply electricity for domestic or rural use of the land.
A wind energy facility requires a transmission or distribution system of power lines, including substations, converter installations, and other works to connect the wind energy facility to the electricity network. While the transmission or distribution system is generally off-site and distant from the wind energy facility, proponents often seek sites close to existing distribution systems.
A planning permit is required to construct any power line or substation connecting the generator to the electricity network if the generator was granted planning approval after 15 March 2019. This applies to all energy generation facilities, not just wind energy facilities.
Characteristics of a wind energy facility
Wind energy facilities are typically located on sites with steady winds throughout the year, good road access, proximity to the electricity grid and the grid’s capacity (existing and planned). They can vary considerably in size and scale depending on the physical features of the land, the wind resources available, and the grid capacity available.
A wind energy facility typically includes:
- a series of wind turbines
- one or more substations
- power lines to connect to the electricity network
- a temporary construction compound
- wind monitoring equipment, which can include an anemometer
- access tracks, and
- underground cabling connecting the wind turbines to the on-site metered output point from the converter station where the generated electricity will enter the distribution system. This includes connections from the wind turbines to the onsite substations (i.e. an electricity generation, transmission and distribution system where voltage is transformed from high to low, or the reverse, using transformers).
A larger facility may also include:
- a quarry
- concrete batching plant(s)
- an operations and maintenance facility
- a battery energy storage system.
Wind turbines in new wind energy facilities are typically large, rotating, three-bladed machines that produce more than 4.0 MW of electrical output.
Most wind turbines have a generator and rotor blades mounted on top of a steel tower. The rotor blades rotate horizontally, and the turbine’s total site can be as high as 220 to 280 metres.
Who assesses a wind energy facility?
The Minister for Planning is responsible for administering the Environment Effects Act 1978 and deciding whether an Environment Effects Statement (EES) is required under that Act. If a proposal is likely to have a significant effect on the environment, the proponent should refer it to the Minister for a decision on the need for an EES.
If an EES is not required the planning permit process will need to be followed. Clause 72.01-1 of the VPP specifies that the Minister for Planning is the responsible authority for considering and determining planning permit applications for the use and development of land for a:
- energy generation facility, which includes a wind energy facility with an installed capacity of 1 megawatt or greater, and
- utility installation used to:
- transmit or distribute electricity
- store electricity if the installed capacity is 1 megawatt or greater.
Other statutory approvals
In addition to planning requirements for a wind energy facility, proponents should be aware that there may be other local, state and national regulatory requirements.
Some approvals must be obtained before a planning permit application can be determined.
Early consideration of these matters can reduce delays in determining a planning permit application.
Other statutory approvals under the following acts may also be required:
- For Victoria:
- Environment Protection Act 2017
- Aboriginal Heritage Act 2006
- Water Act 1989
- Heritage Act 2017
- Wildlife Act 1975
- National Parks Act 1975
- Livestock Disease Control Act 1994
- Flora and Fauna Guarantee Act 1988 (FFG Act)
- Catchment and Land Protection Act 1994 (CaLP Act)
- Road Management Act 2004
- Mineral Resources (Sustainable Development) Act 1990
- For the Commonwealth:
- Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)
- Native Title Act 1993
The onus is on the proponent to contact the relevant agency to determine its requirements.
What landholders should consider before entering into commercial agreements
Here are some useful links for landholders who are considering entering into commercial agreements:
More information can be found through the following documents and websites:
VicGrid is a division within the Victorian Department of Energy, Environment and Climate Action (DEECA) which coordinates the overarching planning and development of Victoria’s Renewable Energy Zones (REZs). For more up-to-date information, please visit VicGrid's website.
It is currently developing a long-term plan – the Victorian Transmission Plan - regarding the development of transmission infrastructure projects. For more information regarding transmission line planning and consultations, please visit: Developing the first Victorian Transmission Plan | Engage Victoria